Odimmegwa Johnpeter/Abuja
The Transmission Company of Nigeria (TCN) has informed the public that bulk power supply has been restored to its Katampe 330kV Transmission Substation through the Gwagwalada–Katampe 330kV Line 1 at 4:15pm today, Friday, October 9, 2026. This was contained in a statement signed by the Management of TCN.
The statement reads: “The restoration follows the earlier loss of supply through the Shiroro-Katampe 330kV Line 1, which remains out of service due to a fault.
“Meanwhile, the planned maintenance work on the Gwagwalada-Katampe 330kV line 1, involving the replacement of defective line isolators and the associated earthing switch, has been suspended to enable the line supply Katampe 330kV Transmission Substation.
“TCN apologises for any inconvenience caused to electricity consumers in the affected areas, ” it also added.
END